Intersection Work Nearing Completion

Work on the Balmoral and Harbour Expressway intersection is just weeks away from being finished.

City Project Engineer Mike Vogrig tells us the contractor is currently finalizing the traffic signal work.

He adds over the next two weeks they will be removing the old signals, completing curbing, and island paving.

Paving the road should be taking place at the end of next week or the week after.

Following that it should be another couple weeks then the line painting will be completed.

Staff photo

  • Originally from southern Ontario, Jason found his way here and fell in love with the community and music scene of Thunder Bay over twenty years ago. In between various stints on radio, television and writing, Jason is a dad, a partner and (some would consider) a zoo keeper (seriously, he has a LOT of pets).